Fabrication and installation of a steel slab reheat furnace, Port Kembla, NSW •Contractor’s Project Manager & overseas Procurement Manager. •Manage a Consortial agreement with the international technology supplier •Installed 2400 tonne of fabricated steel of which 700
tonne was procured, fabricated and painted in Vietnam. •3 km of pipes, 1500 valves, 8 different fluid & gas systems •2000 tonne of refractory installed.
Click HERE for large image |
|
|
|
Removal of asbestos roof tiles and pipe lagging,
building remediation and re-cladding of Ryde
water pumping station, western Sydney.
•Contractor’s Project Manager. •Critical OHS&E procedures. •Plant operating during strip out.
Click HERE for large image
|
Upgrade of a basalt quarry’s crushing and screening circuit, Illawarra region, NSW •Principal’s Representative •Assessed performance of existing material handling, crushing
screening facilities •Developed and costed plant upgrade options for the client’s
consideration
•Prepared the capital budgets for the selected option •Prepared technical scopes and contracts for the designers,
detailers, OEM suppliers, mechanical/structural, electrical
and civil contractors. •Managed the execution of the works and commissioned the
upgraded plant
Click HERE for large image
|

|

|
Importation of a 250 tonne drop ball crane for a steel
recovery specialist, Port Kembla, NSW.
•Pincipal’s Representative •Liaison required between the supplier, shipper, Port Authority,
AQIS, Customs, RTA, Rail Infrastructure and specialist
transporter.
Click HERE for large image
|
Replacement of a 300t steel-making vessel.
•Project Manager of the Contractor.
•Specialist welding subcontractors to AS1554 Pt 5 welding.
•24 hr / 7 day week 40 day shutdown.
Click HERE for large image |

|

|
Fabrication and installation of the terminal fixed links
at Sydney’s International Airport: •Project Manager of the Contractor. •Complex commercial management. •High component of detail design. •Road transportable modules. •Site installation restricted around an operating airport.